Why does this project need to happen now?
This project was identified as a priority due to the current impacts of flooding to the local community including residences, businesses, hospitals, and transportation.
How does this project benefit Charleston?
The construction of the drainage improvements will ensure less frequent and less extensive flooding. This project also includes components that improve the streetscaping along the Septima Clark Parkway and adjacent roadways.
What is the time frame for construction?
Construction of Phase 1, which started construction of the Project, commenced in 2011 and was completed in 2013. Phase 2 was started in 2015 and was completed in 2017. Phase 3 began in 2016 and finished up in 2020. Current construction on Phase 4 is expected to be complete in 2023. Phase 5, which concludes construction of the Project with the installation of the pumps and pump station superstructure, is expected to be complete in 2025.
Where will construction activities take place?
Aside from some minor work to sever the new system from the existing tidal system at the end of Phase 4, all remaining work will occur between the US17 overpasses adjacent to the Ashley River.
How is the tunnel constructed?
Large diameter (20ft to 30ft) concrete shafts are constructed to depths ranging from 120 to 170ft below ground level. A tunnel boring machine (TBM) is used to excavate the ground starting from one shaft and terminating at another shaft. As the TBM excavation progresses the ground is temporarily supported with lumber and steel. Once excavation is complete, concrete is placed to permanently support the tunnel; the tunnel ultimately acts as a large concrete pipe at the completion of construction.
What type of construction activities will occur?
For Phase 4, construction consists of driving piles to support the pump station and outfall structures, excavation of soil to accommodate concrete placement for the pump station and outfall structures, construction of the wetwell and outfall, construction of a silt removal unit, installation of silt removal pumps, and installation of bar screens to remove trash before the water is discharged to the Ashley River. Phase 5 will consist of installation of the large stormwater pumps, each capable of pumping 120,000 gallons per minute, and construction of the pump station superstructure.
What is the City of Charleston doing to limit construction impacts?
Construction activities are monitored to determine impacts from light, sound, vibration, and ground movement. Construction activities are limited to daytime hours only when possible.
How will noise be controlled around the construction site?
The Contractor must follow applicable OSHA standards and City ordinances regarding noise levels. Construction activities are limited to daytime hours only when possible. Construction activities occurring during nighttime hours are staged to minimize noise when possible.
What safety precautions are being taken?
Signage will be posted at each of the project sites. Fencing is installed around the perimeter of all construction sites to prevent public entry. Additional security measures are installed at the shaft locations to prevent accidental falls once onsite.
Who can I call if there is an emergency?
If there is an immediate concern related to health or property, call 911. Otherwise, call the City of Charleston at 843-724-7311.
How can I contact the City of Charleston or ask questions during the project?
We encourage you to ask questions throughout the project! If there is an immediate concern related to health or property, call 911. Otherwise, call the City of Charleston Citizen Services Desk at 843-724-7311.
Where can I go to stay connected with the project?
citizenservices@charleston-sc.gov
Request to be added to the Spring/Fishburne Project E-Newsletter
Sign up here! http://eepurl.com/g8ylfb